Çamlıca I HPP
Yahyalı/Kayseri
Solar power plants are a profitable energy solution in terms of construction-operation costs and efficiency. For these reasons, they are widely used. Being minimally harmful to nature, they are among the energy production systems of the future.
Facility Power: 93,45 MWe / 130,746 MWmm
Storage Unit: 94 MWe / 94 MWh
EPDK License Number: EÜ/14727-13/06751
License Date: 16.07.2026
License Expiration Date: 16.07.2075
Obtaining the Generation License
EIA Positive Decision (Transmission Line, ETL)
Finalization of Zoning Plan
EIA Positive Decision (Power Plant Site)
The geological and geotechnical study report based on construction was approved.
Pre-Facility Works Protocol was signed.
A public participation meeting was held.
Pre-license numbered ÖN/11944-11/05678 was received from EMRA.