Solar power plants are a profitable energy solution in terms of construction-operation costs and efficiency. For these reasons, they are widely used. Being minimally harmful to nature, they are among the energy production systems of the future.

-

-

Facility Power:  93,45 MWe / 130,746 MWmm

Storage Unit:  94 MWe / 94 MWh

EPDK License Number:  EÜ/14727-13/06751

License Date:  16.07.2026

License Expiration Date:  16.07.2075

Important Stages

  • July 2026

    Obtaining the Generation License

  • April 2026

    EIA Positive Decision (Transmission Line, ETL)

  • March 2026

    Finalization of Zoning Plan

  • January 2025

    EIA Positive Decision (Power Plant Site)

  • December 2023

    The geological and geotechnical study report based on construction was approved.

  • Already approved.

  • November 2023

    Pre-Facility Works Protocol was signed.

  • A public participation meeting was held.

  • July 2023

    Pre-license numbered ÖN/11944-11/05678 was received from EMRA.